If you want a solar system (Small Household Power Plant – HMKE), you have to go through two basic processes – either partly alone or with the help of a competent service provider: 1: Authorization, 2: Installation (and then connection to the system).
Without them, a solar producer cannot be put into operation today. Most solar installation companies will help you go through these steps. We’ve written down what you need to do if you start HMKE licensing and solar system installation.
1: Authorization
Here you can see the full HMKE licensing process. If you want to get started, you will find all the necessary materials in the downloadable documents. If you don’t want to deal with these, simply fill out a power of attorney and we’ll take care of the whole process for you in one step.

Claim
 
up to 1-2 days
Submit the HMKE claimant to your service provider about your planned system.
Who does
the builder of the system - You
Technical inspection
 
up to 30 days
Your service provider will examine whether the planned system is appropriate and feasible at the site.
Who does
your service provider
Planning, starting licensing
up to 90 days
 
Preparation and licensing of the technical plans of the actual system.
 
 
Who does 
designer or solar company
 
Security, high yields -
all you have
to do is
install
2: Telepítés
A telepítés azután kezdődhet el, hogy a szolgáltató a Terv vizsgálat során jóváhagyta a fejleszteni kívánt rendszerre beadott összes dokumentumot. Ezután 180 nap áll az Ön rendelkezésére, hogy az engedélyeztetett termelőt kiépítse. Ha lecsússza ezt az időpontot, újra kell kezdenie az Igénybejelentéstől.

Plan examination
  up to 1-2 days
 
Your service provider will examine whether the planned system is appropriate and feasible at the site.
 
 
Who does
  az Ön szolgáltatója
 
Installation
up to 180 days
It installs a licensed system designed for your capabilities. This is 1-10 days depending on demand.
Who does
solar company
System connection
up to 15 days + disembarkation
After the system is ready to be reported, the service provider will perform the necessary meter replacement / parameterization.
It can then be commissioned.
Who does
your service provider
0 forint
account,
secure future, risk-free investment
Documents, useful links for HMKE licensing

- HMKE application form
- Phase extension request
- Registered electricians
- HMKE claim notification

- HMKE application form
- Phase extension request
- Registered electricians
- HMKE claim notification

- HMKE application form
- Phase extension request
- Registered electricians
- HMKE claim notification
What do we prefer for you?
You don’t have to deal with the whole licensing if you build your solar system with us. Simply download this power of attorney, complete it, print it out, and send it to us signed. We do the rest.